Synchronizing structure and diagrams from SAP Solution Manager to Celonis Process Management
Mapping of structure elements
The elements are going to be synchronized following the table below:
SAP Solution Manage | Celonis Process Management |
---|---|
Folder | Category |
Scenario | Main Process |
Process | Main Process |
Diagram a | SubProcess A |
Diagram b | SubProcess B |
Diagram c | SubProcess C |
This way, if the process has multiple diagrams, all of the diagrams will be synchronized.
Synchronizing diagram elements
The diagram will be synced if the type is "Process" or "Collaboration" but only with one original pool. The diagram will be synced if the sub type is "By Role", but if the sub type is "By System", the diagram will not be synchronized.
SAP Solution Manage | Celonis Process Management |
---|---|
events (start, end, intermediary) | appropriate events |
gateways | appropriate gateways |
draft task | local task |
process step reference | local task with appropriate bpt attached |
empty sub process | interface |
Synchronizing sub process reference
For the sub process reference elements to be synchronized correctly some conditions have to be met:
- Sub process has to be referenced to the process;
- Sub process reference has to the attached to one diagram, or if it has multiple, one has to be set as the default.
If the sub process reference does not have a link to a concrete diagram, or it has more diagrams attached but no default is set, the sub process will be synced like an interface with an empty placeholder. If the conditions are met, the sub process reference will be synced like a sub process reference shape.
Process of synchronization
To synchronize the structure from SAP Solution Manage to Celonis Process Management go to Processes > architecture and click the SAP button. Then click Synchronize best practice package.
A dialog will open. Choose what scope you want to sync, or if you leave it empty, the entire structure will be synced. When the synchronization is done there will be a new category added to the process house element. The entire synchronized structure will be in this category. The elements will be released and not editable. For now you can copy only diagram elements to another structure.
If a synchronized Task has an attached Best Practice Task, the Application and Application service that are attached to that Best Practice Task are also visible in the detail content of the Task: